Diesel Generator Maintenance

Preventive 500 KVA:

The following daily check as recommended by manufacturer for preventive maintenance of diesel generator :

  • Fuel level……………………………………………Check
  • Radiator Water Level………………………………Check
  • Lubricating oil level ………………………………..Check
  • Air inlet filter.…………………………………………Check
  • Engine coolant level……………………………….. Check
  • Fan, cooling………………………………………….Check
  • Crankcase Breather tube………………………….. Check
  • Drive belts…………………………………………… Check
  • Engine mounts……………………………………… Check
  • Engine air cleaner service indicator………………  Check
  • Battery cable and connection……………………….Check
  • Generator room clean properly.

Diesel Generator Maintenance – Preventive  – work at every 150 hrs

  • Lubricating oil & lubricating oil filter change.
  • Air filter clean.
  • Clean cooling tank
  • Fuel filters change.
  • Change radiator water and mixed coolant.
  • Fuel filters water separator change.
  • Air filters restriction check & correct.
  • Battery water check or refill.

Diesel Generator Maintenance – Preventive – work at every 300 hrs

  • Lubricating oil & lubricating oil filter change.
  • Air filter change.
  • Fuel filters change
  • Change radiator water and mixed coolant.
  • Fuel filters water separator change.
  • Air filters restriction check & correct.
  • Battery water check or refill.

Diesel Generator Maintenance – Preventive – work at every 450 hrs

  • Lubricating oil & lubricating filter change.
  • Air filter clean.
  • Fuel filters change.
  • Change radiator water and mixed coolant.
  • Fuel filters water separator change.
  • Air filters restriction check & correct.
  • Battery water check or refill.
  • Water filters change.

Diesel Generator Maintenance – Preventive  – work at every 600 hrs

  • Lubricating oil & lubricating oil filter change.
  • Air filter………………………………………Change/ if needed
  • Fuel filters change
  • Change radiator water and mixed coolant.
  • Fuel filters water separator change.
  • Air filters restriction check & correct.
  • Battery water check or refill.
  • Overhead set ………………………………..Adjust
  • Engine wiring harness………………………Check/replace if need.
  • Engine cranking breather……….…………..Clean
  • Ignition system……………………………….Check /Replace
  • Supplement coolant additive as needed…..Check/add

Diesel Generator Maintenance – Preventive  – work at every 750 hrs

  • Lubricating oil & lubricating oil filter change.
  • Air filter clean.
  • Fuel filters change.
  • Change radiator water and mixed coolant.
  • Fuel filters water separator change.
  • Air filters restriction check & correct.
  • Battery water check or refill.
  • Ignition fuel system……………………… Check/Replace if needed
  • Supplemental coolant additive…………..Check / Test
  • Stator leads connection…………………..Check/Connect if needed

Diesel Generator Maintenance – Preventive – work at every 900 hrs

  • Lubricating oil & lubricating oil filter change.
  • Air filter change.
  • Fuel filters change
  • Change radiator water and mixed coolant.
  • Fuel filters water separator change.
  • Air filters restriction check & correct.
  • Battery water check or refill.
  • Fuel injector and fuel system..………Change/replaced if needed
  • HP fuel pump…………………………. Check/replaced if needed
  • Fuel pressure maintaining valve……. Check/replaced if needed
  • Engine Mounts……………………..…..Check/replaced if needed
  • Engine Protective Devices……………Replace/Check
  • Starting motor ………………….………Inspect/correction if needed
  • Water pump (HT & LT)………………….Inspect/correction if needed
  • Main alternator…………………………Check

L/C for a Diesel Generator

Dated: 08/09 /2010

To                                                                             

The Manager,

Prime Bank Ltd.

Motijheel Branch,

Dhaka,

Sub:    Request to open capital machinery L/C for EUR9O: 1309000.00 taking facilities 10%margin and balance by creating HP loan.       

Dear Sir,

We would like to inform that we have already taken a step to produce more with enhancing our factory for new garments order. Now we need to import 1(ONE SET) GENERATOR as our need based. it is mentioning that our previous  generator support is  not good enough to our factory. To meet current electricity crisis  we need to depend to import new one which electricity capacity is 12500KVA WILL BE ADDED OUR PREVIOUS. Now we like to enjoy the said amount HP loan for five years  by creating a installments with one year grace period. The loan will be adjusted from our respective export proceed. it may be mentioned that we have already been enjoying a HP limit with your sanction whereas some loan was adjusted as a very short time facing your sanctioned grace period. The supplier details and offer are given as below:-

1) M/S MTU ASIA PTE LTD for EURO: 13088000.00(DIESEL GENERATOR 12850KVA

As such we request to kindly sanction a HP loan for 1373064.00 with taking10% margin from our available fund.

The relevant copy of proforma invoice and other documents are attached herewith for your kind information and necessary action.

Thanking you in anticipation.

Yours faithfully,

Dr. Habib

Certificate As Diesel Generator Maintenance Operator

This is to Certify that we the supplier of Perkins 2800 Series model 2806C-E16 Diesel Generator  have trained Mr. ABUL Hasim Son of Abdul Hannan Hawlader of Village : Baliafag, PO: Khoidfdfrabad PS: Bakergong, District : Barisal. Working in Auto GROUP on operating and troubleshooting of the supplied Generator.